June 2025
Options Energy Group is working on behalf of SSE and have a linkbox that requires replacement. The location of the works is at the side of Williams Chartered Accountants near the junction of Acton Lane and Park Royal Road. In order to undertake these works they require the use of multiway signals at this junction.
Estimated works date: 18/06/2025 – 01/07/2025.
June 2025
Traffic Updates: Old Oak Common and North Acton
Work Item Summary
Project Phase: Phase 1
Region: Old Oak and North Acton
Location: Old Oak Common, Old Oak Common lane, Wells House Road
Worksite Name: North Acton, Old Oak Common
Contractor: BBVS JV, SCS JV
Type of works: Lane closure, Road closure, Traffic management
Estimated Start Date: 15/07/2024
Estimated End Date: 30/04/2027